Greene Construction completed renovations to both the Operating and Radiology
Departments at Children's Hospital Boston at Waltham campus.
The new Operating and supporting Central Sterilization Processing Departments
were constructed in adjacent buildings over two floors. The
Radiology Department was constructed on the first floor in the existing Radiology Building. G. Greene met the
challenge of simultaneously completing both projects in just six months meeting
an extremely aggressive schedule. The new Operating Department includes a connecting bridge on the
third floor between the Amesbury and DeVincent buildings to provide patients
with a clean and sterile environment from pre-operative services to the
operating department. This department includes patient waiting areas,
nurse's stations, six pre-operative bays, 18 PACU bays, six operating rooms
with three scrub/sub sterile units, as well as the Central Sterilization
Processing Department.The Radiology Department includes all the facility's
radiographic equipment. G. Greene was responsible for providing the
infrastructure for all the medical equipment including a CT scan and MRI.
The scope of work included construction of two Radiology and Ultra-sound rooms,
nurse's station, patient-waiting areas, and a Radio-Fluoroscopy and Nuclear
Medicine rooms.
|
 |
|
|
|