Completed at a brisk pace of ten weeks, G. Greene Civil & Utilities Division installed new underground drainage under Mechanic Street in Natick, MA. We portioned the work in two phases and coordinated work with Eversource labor.
Approach
Proactively identified underground storage structures that interfered with underground utilities
Installed temporary water bypass to supply water to buildings located off Mechanic Street
Results
Obtained necessary permits, including Town of Natick trench permit
Sawcut and removed asphalt
Installed drainage lines, manholes, and catch basins